单选题What should be done to add lines from a Purchase Request (PR) to a Requests for Quotation (RFQ)? ()A Hyperlink to the PR tab and add each line.B Go to the Vendors tab in the RFQ application and click Create PO.C Go to the Quotation tab in the RFQ ap...
Sunday, May 5, 2024
单选题What must be created before populating the Tools application? ()A Item SetsB Item Master OwnerC Vendors for the ItemsD Storeroom assignment...
Sunday, April 28, 2024
单选题What is the maximum value (as a percentage of total cost) that an item identified as condition-coded can have?()A 25%B 50%C 75%D 100%...
单选题The IBM Maximo Asset Management V6.2 administrator creates a new Start Center with updated Key Performance Indicators. Which application must be used to associate the Start Center to users? ()A UsersB PeopleC OrganizationsD Security Groups...
单选题Which statement is true about items that have been assembled into a kit? ()A Only rotating items can be part of a kit.B Kits can be assembled from lotted items.C Kits can be assembled from items in different storerooms.D Items that have been assem...
单选题In order to use the item records at the site level, to what must the item be added? ()A AssetB LocationC StoreroomD Rotating Asset...
单选题Which status will prevent an invoice from being cancelled? ()A HoldB EnteredC ApprovedD Waiting for Approval...
单选题What does the ABC designation include for inventory items? ()A Quantity reserved in stockB Quantity expired for a particular LotC Count Frequency in number of daysD Activity Based Costing in capital dollars...
单选题The Client has requested that once Terms and Conditions (Ts Cs) are attached to another record, the Ts Cs should be unchangeable. How is this appropriately accomplished?()A In the Contracts application, delete the Ts Cs from the record and enter a new...
单选题In IBM Maximo Asset Management V6.2, what does the Purchase Orders applications Distribute Costs action do?()A Distribute the line item cost among all lines.B Distribute the line item cost among all direct issue lines.C Distribute the line item cost...
单选题A work order has been created to perform corrective maintenance on a defective generator. All required information has been provided in the work order, but required materials are not in stock and have to be ordered. What is the status of the work ord...
多选题Which two applications can be used by a user to report emergency work, if the user at least wants to report downtime, classify the request, and report actuals?()AJob PlanBQuick ReportingCLabor ReportingDWork Order TrackingEAssignment Manager...
单选题What should be done if a company decides to stop doing business with a vendor? ()A Notify buyers using Workflow.B Delete the Company Master record.C Set the Company record status to DISQUAL.D Check the Disqualified Vendor check box on the Company r...
单选题Through which action are Currency Codes created? ()A select New Row in Currency Codes applicationB select Action Currency Codes in the Database Configuration applicationC select an Organization in the Currency Codes application and add a new rowD ...
单选题At which level do Commodity Codes exist within IBM Maximo Asset Management V6.2? ()A Set levelB Site levelC System levelD Organization level...