130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter

题目

130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A. Conceptual, charter/baseline.

B. Conceptual, master schedule.

C. Development, charter/baseline.

D. Development, master schedule.

E. Development, masterplan